A project being analyzed by PERT has 60 activities, 13 of which are on the critical path. If the estimated time along the critical path is 214 days with a project variance of 100, what is the probability that the project will take 224 days or more to complete?

+5
Answers (1)
  1. 21 April, 09:48
    0
    Step-by-step explanation:

    What is given:

    Formula to be used Z = (X - mean) / standard deviation

    Mean = 214

    X = 224

    Variance = 100

    Formula of Standard deviation = sqrt (variance) = sqrt (100) = 10

    So Z = (224 - 214) / 10 = 10/10 = 1

    For z = 1, the probability is 0.3413; 34.13% ⇒ The probability of project being completed by 224 days is 34.13%
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “A project being analyzed by PERT has 60 activities, 13 of which are on the critical path. If the estimated time along the critical path is ...” in 📗 Mathematics if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.
Search for Other Answers