Ask Question
31 March, 04:36

Our peak time this week will be 8:00a. m to 12:00 p. m which requires 32% more than the afternoon requirements of 473 agents

+5
Answers (1)
  1. 31 March, 04:39
    0
    Let x be the number of agents required during peak hours. This value should be 32% more than the given number of agents in the afternoon which is 473.

    x = 473 + 0.32 (473)

    x = 624.36

    Since, we cannot have the number of agents in decimal place, we round up the value. Thus, the number of agents required during peak hours is approximately equal to 625.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Our peak time this week will be 8:00a. m to 12:00 p. m which requires 32% more than the afternoon requirements of 473 agents ...” in 📗 Mathematics if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.
Search for Other Answers