Ask Question
8 June, 05:26

Six machines, each working at the same constant rate, together can complete a certain job in 12 days. How many additional machines, each working at the same constant rate, will be needed to complete the job in 8 days? A. 2

B. 3

C. 4

D. 6

E. 8

+5
Answers (1)
  1. 8 June, 05:55
    0
    B

    Step-by-step explanation:

    6 machines complete the job in 12 days;

    the more machine you have faster the job will be done, inverse proportion

    6 machines - - - 12 days

    x machines - - 8 days

    you reduce the number of days by a factor of 1.5 (12/1.5)

    sou you hvae to increase the number of machines by 1.5

    6 x 1.5 = 9, so you will need 3 additional machines
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Six machines, each working at the same constant rate, together can complete a certain job in 12 days. How many additional machines, each ...” in 📗 Mathematics if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.
Search for Other Answers