If 10 men can complete a piece of work in 30 days how many men are requiredto complete the same job in 25 days?

+2
Answers (1)
  1. 6 June, 12:41
    0
    We must assume that all workmen work at the same rate, and keep it up forever.

    More men = = > fewer days

    so the proportion is: 30/25 = x/10

    Cross-multiply the proportion:

    300 = 25 x

    Divide each side by 25:

    x = 300/25 = 12 men