10 road workers take 5 days to complete a road repair, working 2 hours a day. How many days would it take 2 people working 5 hours a day to finish a repair?

+2
Answers (1)
  1. 14 November, 10:40
    0
    10 days, 10 workers, 5 days, 2 hours a day = 100 total hours of work. So 2 people working 5 hours a day is 10 hours total. 10 x 10 is 100 so 10 days
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “10 road workers take 5 days to complete a road repair, working 2 hours a day. How many days would it take 2 people working 5 hours a day to ...” in 📗 Mathematics if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.