To complete a task in 15 days a company needs 4 people each working for 8 hours per day. the company decides to have 5 people each working for 6 hours per day. assume that each person works are the same rate. how many days will the task take to complete?

+1
Answers (1)
  1. 7 April, 20:49
    0
    It would take 16 days

    explanation

    if it takes 15 for 4 people to work 8 hours to complete the task, it would be a total of 480 hours. I multiplied 15x4x8. i multiplied 5x6 to get 30. I have to find the third value so i divided 30 from 480 to get 16.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “To complete a task in 15 days a company needs 4 people each working for 8 hours per day. the company decides to have 5 people each working ...” in 📗 Mathematics if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.