Ask Question
30 September, 19:56

It takes 24 electricians 36 days to wire a new housing subdivision. How many days would 32 electricians take to do the same job?

+5
Answers (1)
  1. 30 September, 20:16
    0
    Answer: 27 days

    Step-by-step explanation:

    Hi, to answer this question we have to apply inverse relation:

    Since it takes 24 electricians 36 days to wire a new housing subdivision, the relation is:

    24 (36)

    For 32 electricians:

    24 (36) = 32 (x)

    Solving for x (days)

    864 = 32x

    864/32 = x

    x = 27 days

    Feel free to ask for more if needed or if you did not understand something.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “It takes 24 electricians 36 days to wire a new housing subdivision. How many days would 32 electricians take to do the same job? ...” in 📗 Mathematics if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.
Search for Other Answers