The design of a concrete mix requires 2,314 lb/yd3 of gravel having a moisture content of 3.5% and absorption of 4.2%, and 899 lb/yd3 of sand having a moisture content of 5.7% and absorption of 1.4%, and 244 lb/yd3 of free water. What is the weight of the mixing water per cubic yard that should be used at the job site?
+1
Answers (1)
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “The design of a concrete mix requires 2,314 lb/yd3 of gravel having a moisture content of 3.5% and absorption of 4.2%, and 899 lb/yd3 of ...” in 📗 Mathematics if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.
Home » Mathematics » The design of a concrete mix requires 2,314 lb/yd3 of gravel having a moisture content of 3.5% and absorption of 4.2%, and 899 lb/yd3 of sand having a moisture content of 5.7% and absorption of 1.4%, and 244 lb/yd3 of free water.