If a new sidewalk will be 5 feet wide, 100 feet long and filled to a depth of 9 inches (0.75 foot) with concrete how many cubic yards of concrete are needed

+3
Answers (1)
  1. 25 November, 15:10
    0
    (5 ft) * (100 ft) * (0.75 ft) * ((1 yd) / (3 ft)) ³ ≈ 13 8/9 yd³

    About 13.89 cubic yards of concrete are needed.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “If a new sidewalk will be 5 feet wide, 100 feet long and filled to a depth of 9 inches (0.75 foot) with concrete how many cubic yards of ...” in 📗 Mathematics if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.