If 12 workers can do piece of work in 20 days how many workers should be added to complete the work in 16 days

+4
Answers (1)
  1. 10 February, 12:20
    0
    Step-by-step explanation:

    Indirect proportion. If no. of workers increased, the working days will be decreased.

    No: workers to complete in 16 days = 20 * 12 / 16 = 5 * 3 = 15 workers

    3 more workers should be added to complete the work in 16 days