A project manager has determined that of the work for a project was completed in 9 days. How many more days will it take to finish the project if the work continues to progress at the same rate?

6

7

10

21

27

+3
Answers (1)
  1. 20 December, 20:29
    0
    The Correct Answer Is 6
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “A project manager has determined that of the work for a project was completed in 9 days. How many more days will it take to finish the ...” in 📗 Mathematics if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.