A recycling plant processes an average of 1/3

ton of glass each minute at approximately what rate does the recycling plant process class, and times per day? (1 day = 24 hours)

+2
Answers (1)
  1. 24 May, 02:23
    0
    The solution to this problem is to convert 1/3 tons/minute to the number of tons/day.

    This is done by multiplying 1/3 tons/minute by 60 minutes/hour and by 24 hours/day.

    Looking the units of measure, we see that the minutes will cancel and the hours will cancel; and we will be left with tons/day. To determine how many, multiply (1/3) x 60 x 24. I will leave the calculation to you, but you should get 480.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “A recycling plant processes an average of 1/3 ton of glass each minute at approximately what rate does the recycling plant process class, ...” in 📗 Mathematics if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.