Crew a can tunnel through a mountain in 30 days. if crew B starts from the other side at the same time, the tunnel can be completed in 18 days. how long would it take crew B working alone?

+1
Answers (1)
  1. 3 August, 09:11
    0
    39 days because 1/2 of 18 = 9 and 9 plus 30 = 39
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Crew a can tunnel through a mountain in 30 days. if crew B starts from the other side at the same time, the tunnel can be completed in 18 ...” in 📗 Mathematics if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.