Which of the following source documents is used to summarize all of the costs incurred for a specific job?

+2
Answers (1)
  1. 14 October, 19:04
    0
    job cost sheet.

    Step-by-step explanation:

    When planning or working on a specific project/job all the actual costs that are incurred for that job are written down in the job cost sheet. This report is an entire compilation that should be created by the accounting department and then distributed to all the members of the management department who then analyze it and determine whether the job was correctly bided. This sheet gets updated as the job is undergoing and fully completed when the job is closed.