Ask Question
24 September, 19:08

To complete a task in 16 days a company needs

5 people each working in 6 hours per day

The company decides to have

8 people each working in 4 hours per day

Assuming that each person works at the same rate, how many days will the task take to complete

+4
Answers (1)
  1. 24 September, 19:19
    0
    15 days

    Step-by-step explanation:

    Total hours required =

    16*5*6 = 480

    Let n be the no. of days

    480 = n*8*4

    480 = 32n

    n = 480/32

    n = 15
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “To complete a task in 16 days a company needs 5 people each working in 6 hours per day The company decides to have 8 people each working in ...” in 📗 Mathematics if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.