It takes 15 electricians 24 days to wire a new housing subdivision. How many days would 18 electricians take to do the same job, assuming all electricians work at the same pace?

+4
Answers (1)
  1. 26 December, 16:27
    0
    So to set up this equation, you have to do

    Time1*Workers1=Time2*Workers2

    In this case, Time1=24 days, Workers1=15 electricians, and Workers2=18 electricians, and we have to solve for Time2

    Thus we get 15*24=18*Time2

    Time2=15*24/18=20 days
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “It takes 15 electricians 24 days to wire a new housing subdivision. How many days would 18 electricians take to do the same job, assuming ...” in 📗 Mathematics if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.