One-half of a road construction project was completed by 6 workers in 12 days. working at the same rate, what is the smallest number of workers needed to finish the rest of the project in exactly four days?

+4
Answers (1)
  1. 21 December, 19:42
    0
    6 workers*12 days=x workers*4 days

    x=6*12/4=3*6=18 workers are needed
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “One-half of a road construction project was completed by 6 workers in 12 days. working at the same rate, what is the smallest number of ...” in 📗 Mathematics if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.