Seven people can paint a bridge in 15 days.

a) How long will it take 3 people to paint the bridge?

b) The bridge was painted in t days, write down an expression, in terms of t, for the number of people needed to paint the bridge

+3
Answers (1)
  1. 1 July, 08:07
    0
    a) 3 people will need 35 days to paint the bridge

    b) p=105/t

    Step-by-step explanation:

    a)

    We have 7 people each one is to work 15 days, so the bridge needs a total of 7 (15) days of work

    7 (15) = 105

    Then we have 3 people each one is to work t days, altogether should do a total of 105 days of work

    3 (t) = 105

    Solve for t

    t=35

    b)

    Substitute p for 3 in the second equation

    p (t) = 105

    Solve for p

    p=105/t
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Seven people can paint a bridge in 15 days. a) How long will it take 3 people to paint the bridge? b) The bridge was painted in t days, ...” in 📗 Mathematics if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.