You work as a coordinator for data entry projects. On one project, the status report shows that 15% of the work was completed in 6 days. If the work progresses at the same rate, how many more days will be required to complete the remainder of the project?

+5
Answers (1)
  1. 8 March, 10:27
    0
    The remaining 85% will take 85/15 * 6 days = 34 days to complete.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “You work as a coordinator for data entry projects. On one project, the status report shows that 15% of the work was completed in 6 days. If ...” in 📗 Mathematics if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.