Ask Question
10 March, 18:39

A company had the following direct materials cost information:

Standard costs assigned: Direct materials standard cost (405,000 units @ $2/unit) $810,000

Actual costs: Direct Materials costs incurred (403,750 units @ $2.20/unit) $888,250

What was the cost variance?

a) $2,500 Favorable.

b) $78,250 Favorable

c) $78.250 Unfavorable

d) $80,750 Favorable.

e) $80,750 Unfavorable.

+2
Answers (1)
  1. 10 March, 19:07
    0
    Option c) $78,250 unfavorable

    Step-by-step explanation:

    The given information in the question:

    Standard cost = $810,000

    Actual cost = $888,250

    Cost variance can be calculated as using the following formula:

    Cost variance = standard cost - actual cost

    = 810,000 - 888,250

    = ($78,250) unfavorable

    Favorable indicates how much under budget the project.

    unfavorable indicates how much over budget the project.

    Therefore, Option c) 78,250 unfavorable is the answer.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “A company had the following direct materials cost information: Standard costs assigned: Direct materials standard cost (405,000 units @ ...” in 📗 Mathematics if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.
Search for Other Answers