Ask Question
18 November, 16:45

You work as a coordinator for data entry projects. On one project, the status shows that 15% of the work was completed in 6 days. If the work progresses at the same rate, how many more days will be required to complete the remainder of the project.

+4
Answers (1)
  1. 18 November, 16:52
    0
    Answer: 36 more days

    Step-by-step explanation:

    it averages out to 2.5% per day
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “You work as a coordinator for data entry projects. On one project, the status shows that 15% of the work was completed in 6 days. If the ...” in 📗 Mathematics if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.