How many cubic yards of dirt must be removed when digging a foundation for a building if the excavation is 94 ft. long and 36 ft. wide and 24 ft. deep?

+3
Answers (1)
  1. 18 September, 20:03
    0
    We have to calculate how many cubic yards of dirt must be removed. First we have to convert feet to yards:

    1 yard = 3 ft

    L = 94 ft : 3 = 31.33 yd

    W = 36 ft : 3 = 12 yd

    H = 24 ft : 3 = 8 yd

    Volume:

    V = L x W x H = 31.33 * 12 * 8 = 3,008 yd³

    Answer : 3,008 yd³.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “How many cubic yards of dirt must be removed when digging a foundation for a building if the excavation is 94 ft. long and 36 ft. wide and ...” in 📗 Mathematics if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.