All members of a construction crew work at the same pace. Four of them working together can pour a foundation in 32 hours. How many hours would the job take if the number of workers: increased 4 times

+3
Answers (1)
  1. 17 June, 08:24
    0
    16 hrs

    Step-by-step explanation:

    4 of them doing it in 32 hrs is the equivalent to 4/8hrs (32hrs) days 32: 4 = 8

    8 of them doing it in 16hrs would be the equivalent to 2/8 hrs (16hrs) days
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “All members of a construction crew work at the same pace. Four of them working together can pour a foundation in 32 hours. How many hours ...” in 📗 Mathematics if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.