If it takes 100 minutes to complete a circuit, demand at the next work center is 5 parts per minute, and a kanban container holds 20 parts, how many containers are required?

+5
Answers (1)
  1. 6 March, 09:08
    0
    5 times 100 = 500

    500 divided by 20 = 25

    25 containers
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “If it takes 100 minutes to complete a circuit, demand at the next work center is 5 parts per minute, and a kanban container holds 20 parts, ...” in 📗 Mathematics if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.