On a new construction site an electrician can install a new light fixture in 20 minutes a project calls for 24 new fixtures to be installed on each of four floors if a work day is 8 hours how many work days will it take to electricians to complete the installations

+1
Answers (1)
  1. 18 April, 00:22
    0
    If there were two electricians, they'd need to install 48 fixtures per person ... if it takes 20 minutes for each fixture, it would take a total of 960 minutes, which converts to 16 hours. If a work day was only 8 hours, it would take two electricians TWO work days to install 96 light fixtures, or 24 light fixtures for four floors.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “On a new construction site an electrician can install a new light fixture in 20 minutes a project calls for 24 new fixtures to be installed ...” in 📗 Mathematics if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.