Ask Question
24 February, 02:42

a person hour is a unit of measure representing one person working for one hour. A construction foreman estimates it will take 2880 person-hours to build a new library. If 12 workers are scheduled to work on the project at the same time, how many hours will it take to complete the project

+4
Answers (1)
  1. 24 February, 03:03
    0
    It will take about 240 hours to complete the project, I am very sorry if my answer is incorrect
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “a person hour is a unit of measure representing one person working for one hour. A construction foreman estimates it will take 2880 ...” in 📗 Mathematics if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.
Search for Other Answers