A construction company plans to invest in a building project. There is a 25% chance that the company will lose $40,000, a 35% chance of a break even, and a 40% chance of a $30,000 profit. Based on this, what should the company do?

A)

The expected value is $2,000, so the company should proceed with the project.

B)

The expected value is $22,000, so the company should proceed with the project.

C)

The expected value is - $2,000, so the company should not proceed with the project.

D)

The expected value is $-22,000, so the company should not proceed with the project.

+3
Answers (1)
  1. 1 December, 05:44
    0
    A) because the expected value is 0.25 (-40000) + 0.4 (30000) = 2000
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “A construction company plans to invest in a building project. There is a 25% chance that the company will lose $40,000, a 35% chance of a ...” in 📗 Mathematics if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.