A project manager has determined that 3/10 of the work for a project was completed in 9 days. How many more days

will it take to finish the project if the work continues to progress at the same rate?

+2
Answers (1)
  1. 8 June, 23:51
    0
    30 days

    Step-by-step explanation:

    3/10 is completed in 9 days, so 6/10 in 18 days and 9/10 in 27 days.

    If it only takes 9 days for 3/10, then 9 divided by 3 = 3. The final 1/10 is completed in 3 days. This all equals 30 days.

    I could be wrong, but that's what I think.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “A project manager has determined that 3/10 of the work for a project was completed in 9 days. How many more days will it take to finish the ...” in 📗 Mathematics if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.