Sam accepted a job to brick a new home. he calculated that he can complete the job in 4 days. he hired a trainee to assist him. he has seen the trainee work and estimates that the trainee working alone would take 6 days to complete the job. how much time should the two of them working together need to brick the house? (round your answer to the nearest tenth.)
+4
Answers (1)
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Sam accepted a job to brick a new home. he calculated that he can complete the job in 4 days. he hired a trainee to assist him. he has seen ...” in 📗 Mathematics if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.