Bonita has a standard of 2 hours of labor per unit, at $12 per hour. In producing 2600 units, Bonita used 5050 hours of labor at a total cost of $61610. Bonita's labor quantity variance is

+5
Answers (1)
  1. 6 September, 22:29
    0
    1800

    Step-by-step explanation:

    Labor quantity variance = Actual quantity * standard price - standard quantity * standard price

    Standard quantity=2*2600=5200

    Labor quantity variance

    5050*12-5200*12=1800
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Bonita has a standard of 2 hours of labor per unit, at $12 per hour. In producing 2600 units, Bonita used 5050 hours of labor at a total ...” in 📗 Mathematics if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.