If the standard to produce a given amount of product is 2,000 units of direct materials at $12 and the actual direct materials used are 1,600 units at $13, the direct materials quantity variance is $5,200 favorable.

+2
Answers (1)
  1. 24 October, 00:07
    0
    The answer is FALSE

    Step-by-step explanation:

    Materials quantity variance = (SQ - AQ) * SP

    = (2,000 - 1,600) * 12

    $4800 Favourable
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “If the standard to produce a given amount of product is 2,000 units of direct materials at $12 and the actual direct materials used are ...” in 📗 Mathematics if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.