Eighteen men take 15 days

to dig 6 hectares of land

Find the number of men

required to dig 8 hectares

in 12 days?

+2
Answers (1)
  1. 4 June, 22:54
    0
    number of men = 30

    Step-by-step explanation:

    18 men takes 15 days to dig 6 hectares of land.

    18 men will take 12 days to dig? hectares of land

    cross multiply

    hectares of land = 12 * 6/15

    hectares of land = 72/15

    hectares of land = 4.8 hectares

    18 men will take 12 days to dig 4.8 hectares of land

    ? number of men will take 12 days to dig 8 hectares

    cross multiply

    number of men = 18 * 8/4.8

    number of men = 144/4.8

    number of men = 30