10 people can paint a building in 5 days. If each person moves as quickly as others then how much of a building can 7 people paint in 5 days

+3
Answers (1)
  1. 20 September, 20:51
    0
    The entire job is 10*5 = 50

    7 people in 5 days will do 7 * 5. That is 35.

    So, it is 35/50 = 7/10 = 0.7 of the job or 70%.

    Does this make sense?
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “10 people can paint a building in 5 days. If each person moves as quickly as others then how much of a building can 7 people paint in 5 days ...” in 📗 Mathematics if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.