A crew will arrive in one week and begin filming a city for a movie. The mayor is desperate to clean the city streets before filming begins. Two teams are available, one that requires 200 hours and one that requires "400" hours. If the teams work together, how long will it take to clean all of the streets? Is this enough time before the cameras begin rolling?
+3
Answers (1)
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “A crew will arrive in one week and begin filming a city for a movie. The mayor is desperate to clean the city streets before filming ...” in 📗 Mathematics if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.