Tim can shell a bushel of peas in 2 hours. Jill can shell a bushel in 3 hours. How long will it take them to shell a bushel of peas if they work together?

+4
Answers (1)
  1. 28 January, 23:29
    0
    Hence amount of time used by both to shell a bushel of peas working together is 6/5 hrs = 72 minutes

    Step-by-step explanation:

    Amount of time used by Tim is 2hrs

    Amount of work done by Tim in 1hr = 1/2

    Amount of time used by Jill is 3hrs

    Amount of work done by Jill in 1hr = 1/3

    Hence amount of work done by both in 1 hr = (1/2) + (1/3) = 5/6

    Hence amount of time used by both to shell a bushel of peas working together is 6/5 hrs = 72 minutes
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Tim can shell a bushel of peas in 2 hours. Jill can shell a bushel in 3 hours. How long will it take them to shell a bushel of peas if they ...” in 📗 Mathematics if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.