Mr. Cutler makes clay bricks and clay tiles to sell at maker fairs. It takes him 10 minutes to make a brick and 20 minutes to make a tile. Each brick

uses 3 pounds of clay and each tile uses 2 pounds of clay. He has 160 minutes available for making the bricks and tiles and has 20 pounds of

clay on hand.

If he makes a profit of $2 on each brick and $3 on each tile, how many bricks and tiles should he make to maximize his profit?

A. Mr. Cutler should make 7 bricks and 2 tiles to maximize his profit.

B. Mr. Cutler should make 7 bricks and 0 tiles to maximize his profit.

C.

Mr. Cutler should make o bricks and 8 tiles to maximize his profit,

D. Mr. Cutler should make 2 bricks and 7 tiles to maximize his profit.

+3
Answers (2)
  1. 30 December, 23:46
    0
    yeah they are correct he should make 2 bricks and 7 tiles
  2. 30 December, 23:55
    0
    Mr. Cutler should make 2 bricks and 7 tiles to maximize his profit.

    Step-by-step explanation:

    Let the no. of bricks be 'b'

    Let the no. of tiles be 't'

    Time taken for 1 brick = 10 mins

    Time taken for 1 tile = 20 mins

    Clay used for 1 bick = 3 pounds

    Clay used for 1 tile = 2 pounds

    Profit on each brick = $2

    Profit on each tile = $3

    Total time available = 160 mins

    Total clay available = 20 pounds

    10b + 20t = 160

    b + 2t = 16

    b = 16 - 2t

    3b + 2t = 20

    3 (16 - 2t) + 2t = 20

    48 - 6t + 2t = 20

    48 - 4t = 20

    -4t = 20-48

    4t = 28

    t = 7

    b = 16 - 2t

    b = 16 - 14

    b = 2

    Mr. Cutler should make 2 bricks and 7 tiles to maximize his profit.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Mr. Cutler makes clay bricks and clay tiles to sell at maker fairs. It takes him 10 minutes to make a brick and 20 minutes to make a tile. ...” in 📗 Mathematics if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.