If 6 workers can cut the grass in 4 hours, how many workers will be needed to cut the grass in 3 hours?

A. 2 workers

B. 8

C. 12

D. 24

+1
Answers (1)
  1. 5 November, 10:49
    0
    The answer for this question is B
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “If 6 workers can cut the grass in 4 hours, how many workers will be needed to cut the grass in 3 hours? A. 2 workers B. 8 C. 12 D. 24 ...” in 📗 Mathematics if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.