The first programmer can write an app in 10 days. The second programmer can finish the same job in 8 days. How long would it take them to finish the job if they were working together?

+4
Answers (2)
  1. 16 September, 07:54
    0
    Answer: 40/9 days

    Step-by-step explanation: let x be the time when they work together

    daily rate of the first programmer = 1/10

    daily rate of the second programmer = 1/8

    daily rate when they work together = 1/x

    Therefore:

    1/10 + 1/8 = 1/x

    solving the equation:

    9/40 = 1/x

    x = 40/9
  2. 16 September, 08:04
    0
    4 4/9 days.

    Step-by-step explanation:

    You work in rates per day, so:

    1/10 + 1/8 = 1/x where x is the number of days working together.

    Multiply through by the LCD 40x:

    4x + 5x = 40

    9x = 40

    x = 40/9 = 4 4/9 days.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “The first programmer can write an app in 10 days. The second programmer can finish the same job in 8 days. How long would it take them to ...” in 📗 Mathematics if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.