Following a severe snowstorm, Ken and Bettina Reeves must clear their driveway and sidewalk. Ken can clear the snow by himself in 3 hours, and Bettina can clear the snow by herself in 4 hours. After Bettina has been working for 1 hour, Kane is able to join her. How much longer will it take them working together to remove the rest of the snow?

+4
Answers (1)
  1. 15 December, 02:41
    0
    Determine how much of the job they have finished by calculating:

    2/4 + 2/6 = 1/2 + 1/3 = 5/6 of the job has been done.

    So, they have 1/6 of the job to go.

    Then we write the following fractional equation:

    t/4 + t/6 = 1/6

    Multiply all by 12 (the LCD) and get

    3t + 2t = 2

    5t = 2

    t = 2/5 hour = 24 minutes.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Following a severe snowstorm, Ken and Bettina Reeves must clear their driveway and sidewalk. Ken can clear the snow by himself in 3 hours, ...” in 📗 Mathematics if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.
Search for Other Answers