All the members of a construction crew work at the same pace. Four of them working together are able to pour concrete foundations in 32 hours. How many hours would this job take if the number of workers:

Increased 2 times

Increased 4 times

+4
Answers (1)
  1. 26 November, 21:17
    0
    1) Increased by 2 times then 16 hours

    2) Increased by 4 times then 8 hours

    Step-by-step explanation:

    Given : -

    ==> 4 construction crew members need 32 hours to pour concrete foundations.

    ==> All the members work at a same pace.

    1) If the numbers of workers are increased by 2 time i. e., 4 workers * 2 = 8 workers. It would take half of the time that is taken now i. e., 32 hours : 2 = 16 hours.

    2) If the numbers of workers are increased by 4 time i. e., 4 workers * 4 = 16 workers. It would take 1/4th of the time that is taken now i. e., 32 hours : 4 = 8 hours.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “All the members of a construction crew work at the same pace. Four of them working together are able to pour concrete foundations in 32 ...” in 📗 Mathematics if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.