seven people need 90 days to repair and paint a heritage building. if the job should be completed in 15 days. how many more people need to be employed.

+1
Answers (1)
  1. 4 May, 17:10
    0
    Here is your answer mate

    Step-by-step explanation:

    As we know that 7 person take 90 days so 1 person takes 90*7=630 days

    As work has to be finished in 15 days than 630/15=42 so

    42 people can complete work in 15 days but as we have already 7 people employed so required are

    42-7=35 so 35 more are needed
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “seven people need 90 days to repair and paint a heritage building. if the job should be completed in 15 days. how many more people need to ...” in 📗 Mathematics if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.