Ask Question
3 June, 10:32

A local project being analyzed by PERT has 42 activities, 13 of which are on the critical path. If the estimated time along the critical path is 105 days with a project variance of 25, what is the probability that the project will be completed in 95 days or less?

+5
Answers (1)
  1. 3 June, 10:43
    0
    the probability that the project will be completed in 95 days or less, P (x ≤ 95) = 0.023

    Step-by-step explanation:

    This is a normal probability distribution question.

    We'll need to standardize the 95 days to solve this.

    The standardized score is the value minus the mean then divided by the standard deviation.

    z = (x - xbar) / σ

    x = 95 days

    xbar = mean = 105 days

    σ = standard deviation = √ (variance) = √25 = 5

    z = (95 - 105) / 5 = - 2

    To determine the probability that the project will be completed in 95 days or less, P (x ≤ 95) = P (z ≤ (-2))

    We'll use data from the normal probability table for these probabilities

    P (x ≤ 95) = P (z ≤ (-2)) = 0.02275 = 0.023
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “A local project being analyzed by PERT has 42 activities, 13 of which are on the critical path. If the estimated time along the critical ...” in 📗 Mathematics if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.
Search for Other Answers