A manufacturer of mountain bikes has found that when 20 bikes are produced per day, the average cost is $200 and the marginal cost is $150. Based on the information, approximate the total cost of producing 21 bikes per day ...?

+2
Answers (1)
  1. 7 November, 09:17
    0
    At 20 bikes, the average cost is $200. This means that each bike costs about $200 to make, thus the total cost for the first 20 bikes is $4000.

    The marginal cost represents the cost of producing one more unit. If the cost of producing a bike after the 20th one (in other words the 21st bike) is $150, then the total cost of producing all 21 bikes is $4150.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “A manufacturer of mountain bikes has found that when 20 bikes are produced per day, the average cost is $200 and the marginal cost is $150. ...” in 📗 Mathematics if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.