The following is a limitation of a bar chart schedule. a. Scheduling information is presented at a summary level b. activity interrelations are not considered c. ease of preparation d. ease of interpretation e. None of the above

+1
Answers (1)
  1. 27 October, 10:55
    0
    b. activity interrelations are not considered

    Explanation:

    A bar chart schedule or Gantt chart is used to visualize task that scheduled over time.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “The following is a limitation of a bar chart schedule. a. Scheduling information is presented at a summary level b. activity interrelations ...” in 📗 Physics if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.