Ask Question
4 August, 02:46

Using the assembly-line balancing procedure, which of the following is the required cycle time in minutes per unit if the daily production time is 480 minutes and the required daily output is 50 units? () (A) 0.104

(B) 50

(C) 9.6

(D) 480

(E) Cannot be determined from the information above

+1
Answers (1)
  1. 4 August, 02:52
    0
    E is the answer because there's not enough information to answer the question
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Using the assembly-line balancing procedure, which of the following is the required cycle time in minutes per unit if the daily production ...” in 📗 Physics if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.
Search for Other Answers