If A, B, and C are three activities connected with SS and FF (combination) relationships with 2-day lag on SS relationship only. Their durations are 5, 10, and 3 respectively. What is the duration of the project? a. 5 days. b. 10 days. c. 3 days. d 18 days.

+2
Answers (1)
  1. 11 March, 03:04
    0
    B. 10 days
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “If A, B, and C are three activities connected with SS and FF (combination) relationships with 2-day lag on SS relationship only. Their ...” in 📗 Physics if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.