Ask Question
24 October, 11:02

Electric power is to be generated by installing a hydraulic turbine-generator at a site 120 m below the free surface of a large water reservoir that can supply water at a rate of 1500 kg/s steadily. Determine the power generation potential.

+4
Answers (1)
  1. 24 October, 11:29
    0
    1764 kilowatt

    Explanation:

    h = 120 m, mass per second = 1500 kg/s

    Power = m g h / t

    Power = 1500 x 9.8 x 120 / 1

    Power = 1764000 Watt

    Power = 1764 kilowatt
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Electric power is to be generated by installing a hydraulic turbine-generator at a site 120 m below the free surface of a large water ...” in 📗 Physics if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.
Search for Other Answers