Electric power is to be generated by installing a hydraulic turbine generator at a site 120 m below the free surface of a large water reservoir that can supply water at a rate of 2400 kg/s steadily. Determine the power generation potential.

+2
Answers (1)
  1. 20 November, 12:36
    0
    2.82 * 10^6 watt

    Explanation:

    H = 120 m,

    Mass per second = 2400 kg/s

    Power = work / time

    Power = m g H / t

    Power = 2400 * 9.8 * 120 / 1

    Power = 2.82 * 10^6 Watt
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Electric power is to be generated by installing a hydraulic turbine generator at a site 120 m below the free surface of a large water ...” in 📗 Physics if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.