Jane is a Product Owner. It is day seven of the Iteration and her team tells her that they may miss their Iteration commitment. What should Jane do?

+2
Answers (1)
  1. 12 February, 19:00
    0
    Support pulling a story that has not been started.

    Explanation:

    To meet up with their iteration commitment, Jane should support pulling a story that has not been started.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Jane is a Product Owner. It is day seven of the Iteration and her team tells her that they may miss their Iteration commitment. What should ...” in 📗 Social Studies if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.