Which of the following describes the finish-to-finish logical dependency? A. The predecessor activity must finish before the successor activity can start. B. The predecessor activity must finish before the successor activity finishes. C. The predecessor activity depends on starting before the successor activity can start. D. The predecessor activity must start before the successor activity can finish.

+1
Answers (1)
  1. 9 December, 20:05
    0
    The correct answer is B. The predecessor activity must finish before the successor activity finishes.

    Explanation:

    Logical dependency is used to describe the connection between different elements especially concerning events or tasks in projects. In this, there are different types of logical dependencies that include start to start, finish to finish, finish to start and start to finish. In the case of finish-to-finish logical dependency, this implies the first task or activity should finish before the second one does, which means activity A and B might develop at the same time but for B to end A needs to end first. Thus, the statement that describes this logical dependency is "The predecessor activity must finish before the successor activity finishes".
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Which of the following describes the finish-to-finish logical dependency? A. The predecessor activity must finish before the successor ...” in 📗 Social Studies if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.
Search for Other Answers